Upgrade to 10.1 Without Virtual WAN Configuration

Important

This upgrade procedure to software release 10.1 assumes that virtual paths are not established between the MCN and Branches.

Note

If you are upgrading from a previous release version such as; 8.1.x, 9.0.x, 9.1.x, 9.2.x; see the instructions provided in the following link: Upgrading to 9.3 without Virtual WAN configuration.

Users upgrading to 10.1 from release version earlier than 9.3 to 10.x, ensure that you upgrade to release version 9.3.3 and then to release version 10.1. In release version 10.0 there is change in database to support RCNs which is not compatible to releases prior to 9.3.3. If you want to revert back to pre-9.3.3 after upgrading to 10.0.2 directly using the Activate Staged option leads to database reset.

Note

If you are upgrading release version 9.3.x or newer, follow the steps below.

Single step upgrade process

On the SD-WAN MCN appliance:

  • You can upload single step upgrade package file; (ctx-sdw-sw-<release.version>.zip).

  • Proceed with Change Management workflow in the GUI.

  • Schedule installs components other than Virtual WAN software.

  1. Prepare Configuration from Configuration Editor and Save configuration with valid name as shown below.

    localized image

  2. Export Save Config file to Change Management by selecting Export button and choose destination as Change Management Inbox.

    localized image

  3. In the Change Management page, upload the ctx-sdw-sw-<release-version>.zip software package file after downloading from the download server, and provide the location from where to upload by selecting ‘Choose Files’.

    localized image

  4. After selecting the files to upload, click upload and a progress bar appears showing the current upload progress.

    localized image

    localized image

  5. After upload is successful, the uploaded files are processed for any invalid errors.

    localized image

  6. After upload processing is successful, information about which platform models the software has been uploaded and processed is displayed.

    localized image

  7. Click Next to proceed with Validation of Configuration file and appropriate message is shown based on the validation results. Accept and proceed with license agreement.

    localized image

  8. The License agreement page for user acceptance is displayed. Click on accept and proceed.

    localized image

  9. After accepting the license successfully you are navigated to Appliance Staging, click on Stage Appliances to proceed.

    localized image

  10. The transfer progress bar appears showing the current preparation and transfer status for each site.

    localized image

  11. After preparing of package is completed, the Transfer Progress bar shows as 100%, click Next and proceed to the activate page.

    localized image

  12. In the Activation page, staged software package can be activated.

    localized image

  13. On clicking Activate Staged, user acceptance pop-up message is displayed. Accept and proceed as shown below.

  14. After accepting the message, click OK. The package gets copied to Appliance Staging state.

    localized image

    localized image

  15. As this is the first time Appliance is being staged, you are redirected to the Local Change Management page for activating the local appliance. After clicking Activate Staged in Local Change Management once again, user confirmation is requested to proceed further. localized image

  16. After accepting, activation starts with a countdown timer of 180s. localized image

  17. After the countdown timer expiration, a message indicating activation has completed is displayed. Click Done.

    localized image

  18. Navigate to Change Management page to download the local change management for respective branches that you need to bootstrap to the network with Virtual WAN software upgrade only, or else move to the next step as shown below.

    localized image

  19. You can enable SD-WAN service and see that virtual paths are up between the branch and MCN.

    localized image

    The Citrix SD-WAN software change management procedure provides the following two different paths for SD-WAN software upgrades:

  20. Using the .zip file to manage upgrades. This process enables in fast package creation times when performing change management.

  21. Using the tar.gz file to manage upgrades. This process is slower than the .zip file process since it creates a full package for all platforms even if only the configuration has changed.

In Citrix SD-WAN release 10 version 1, the software upgrade process using the tar.gz file is improved to increase speed and reduce disk usage compared to the tar.gz file upgrade process in the previous release versions. These improvements are observed when you perform the change management procedure (Configuration update and Software upgrade using tar.gz file) on appliances running SD-WAN release 10 version 1 and higher.

The Citrix SD-WAN appliance GUI displays a message when uploading the software packages. This message is displayed when you click the Stage Appliances button on the Configuration > Virtual WAN > Change Management page. This message appears only when:

  • Adding a software package to the SD-WAN network. For instance, you added a new platform edition to the network and you need

  • Upgrading to newer Citrix SD-WAN release version 10.1.x or higher.

  • Upgrading or downgrading the software release version to release 10.1 or higher.

    localized image

The Change Management optimization message is not displayed when upgrading to Citrix SD-WAN release 10 version 1 from a previous release version.

Note

When using the change management process in Citrix SD-WAN release 10 version 1 while uploading a tar.gz file, disable Single Step upgrade scheduling for WANOP package files, since these files are not available in the tar.gz package.

Upgrade to 10.1 Without Virtual WAN Configuration

In this article